hbhomes
11-06-2009, 19:54 PM
This is an interesting/complex situation.....opinions sought!
We have purchased the shares of a Company that owns the freehold to a block of 12 flats, of which 3 have been newly created on the ground floor and hence no leases have yet been created for these 3 units, although we are in the process of doing this. These 3 flats belong to us.
The remaining 9 flats plus the 3 new flats need to contribute to exterior delapidations which is running into over £200,000. S20 notices were served last year on the leaseholders who were 3 connected parties. So a notice of intent to carry out major works was served, followed by the statement of estimates. Finally a contractor was chosen and a notice of reasons for awarding the contract (although we did not have to, as the cheapest was chosen) was also sent out. Everything fine up to now......
Within the lease it states that a third of the monies in relation to these works can be invoiced and requested up front. Invoices and request have been sent out. No response. It turns out that due to the credit crunch all 9 leasehold properties are in the throws of repossession, with one being sold on and the others about to follow suit.
1) Can I assume that the notices are still all served correctly or do we need to go through the whole process again?
2) Can I now demand payment from the mortgagees/receivers for this initial payment?
3) Do I have to wait until all of the units are resold, which in theory may take some time?
4) One of the flats have gones ahead and resold without the input from the freeholder (I assume as they got a cheap price and wanted/needed to complete; are these buyers now on the hook for these monies?
A slightly unusal situation, but I would be interested in hearing some of the learned views from this messageboard.
Regards
D
We have purchased the shares of a Company that owns the freehold to a block of 12 flats, of which 3 have been newly created on the ground floor and hence no leases have yet been created for these 3 units, although we are in the process of doing this. These 3 flats belong to us.
The remaining 9 flats plus the 3 new flats need to contribute to exterior delapidations which is running into over £200,000. S20 notices were served last year on the leaseholders who were 3 connected parties. So a notice of intent to carry out major works was served, followed by the statement of estimates. Finally a contractor was chosen and a notice of reasons for awarding the contract (although we did not have to, as the cheapest was chosen) was also sent out. Everything fine up to now......
Within the lease it states that a third of the monies in relation to these works can be invoiced and requested up front. Invoices and request have been sent out. No response. It turns out that due to the credit crunch all 9 leasehold properties are in the throws of repossession, with one being sold on and the others about to follow suit.
1) Can I assume that the notices are still all served correctly or do we need to go through the whole process again?
2) Can I now demand payment from the mortgagees/receivers for this initial payment?
3) Do I have to wait until all of the units are resold, which in theory may take some time?
4) One of the flats have gones ahead and resold without the input from the freeholder (I assume as they got a cheap price and wanted/needed to complete; are these buyers now on the hook for these monies?
A slightly unusal situation, but I would be interested in hearing some of the learned views from this messageboard.
Regards
D